OHB wins €102M ESA contract to build ClearSpace-1 debris removal mission

The European Space Agency has awarded German satellite manufacturer OHB a €102 million contract to build ClearSpace-1, a spacecraft intended to capture and remove ESA’s Proba-1 satellite once that satellite is retired from service. The mission is now expected to launch in 2030, years later than originally planned.
The contract was signed on 17 November at Space Tech Expo Europe in Bremen, Germany. It opens the mission’s implementation phase and fixes a design and industrial structure that have changed considerably over the past six years.
From Vega adapter to Proba-1
ESA first contracted the mission in December 2020, awarding €86 million to a consortium led by the Swiss startup ClearSpace. The original plan called for a 2025 launch and the removal of a Vega payload adapter left in orbit after a 2023 launch.
That plan collapsed in August 2023, when space debris struck the adapter. The impact forced a redesign of the mission, and ESA selected Proba-1 as the new target.
In April 2024, ESA announced that OHB would lead the restructured project, with ClearSpace keeping responsibility for close-proximity and capture operations. The new contract formalises OHB’s position as prime contractor for the implementation phase.
Launch vehicle not confirmed
The restructuring appears to have changed the launch arrangements as well. In May 2023, ClearSpace signed a contract with Arianespace to launch the mission on a Vega C in the second half of 2026. A technical paper presented at the 9th European Conference on Space Debris in April 2025 indicated that ClearSpace-1 would instead fly on a dedicated microlauncher.
The vehicle has not been officially named. However, an OHB presentation at ESA’s Clean Space Days in the Netherlands in July 2026 included a mission overview slide, under the heading “Launch Service,” with an illustration that appears to show the RFA ONE rocket.
RFA ONE is being developed by Rocket Factory Augsburg, in which OHB holds a majority stake. OHB’s latest financial report puts the group’s holding at 56.8%. Neither ESA nor OHB has publicly confirmed RFA ONE as the launch vehicle for ClearSpace-1.
Launch timeline
ESA’s news release of 18 November states that the mission is expected to launch in 2030. The OHB presentation from July 2026 narrows that to the second quarter of 2030, though it was delivered several months before the contract signing.
Source: europeanspaceflight.com